Phase 4: Project Execution & Handover

Step 12: Commissioning & Performance Trials

Executing water trials, wet commissioning, and final performance guarantee sign-offs.

1. Pre-Commissioning & Water Trials

Before introducing any biological feedstock or chemicals, the plant must undergo rigorous mechanical and electrical checks:

  • Hydrotesting: Pressure testing of all piping networks, distillation columns, and pressure vessels.
  • Electrical & Instrumentation (E&I) Checks: Loop checking, calibration of control valves, sensors, and safety interlocks.
  • Water Runs: Flushing lines and testing pumps, cooling towers, and the water treatment plant using raw/treated water to verify flow rates and leak-tightness.

2. Wet Commissioning & Performance Guarantee Tests

Once pre-commissioning clearance is signed off by the PMC and Lender's Independent Engineer (LIE), wet commissioning begins:

Test PhaseObjective & Verification Standard
Milling & LiquefactionTest maize milling and slurry preparation with enzyme addition and gelatinization.
Fermentation TrialYeast propagation and batch fermentation tracking conversion efficiency and cycle times.
Distillation & DehydrationProduction of rectified spirit and anhydrous ethanol via molecular sieve unit (99.9% purity).
Continuous Guarantee Run72-hour continuous operation test measuring actual yield (litres/MT grain) and utility consumption (steam/power per litre) against vendor guarantees.

3. Critical Financial Link & Payment Hold Directive

Vendor Payment Hold Directive

Do not release final vendor payments until these guarantees are formally verified on-site. Strict adherence to this milestone protects capital efficiency and ensures all output, yield, and utility specifications are fully satisfied before account closure and commercial handover.